North Carolina transportation officials report that thousands of Hurricane Helene repairs have been completed, but major western North Carolina routes still face years of reconstruction. Recent briefings addressed three separate questions for residents and policymakers: which connections have been restored, what remains unfinished, and how construction affects daily access.

At the North Carolina Board of Transportation’s October meeting in Hickory, Transportation Secretary Daniel Johnson described his recent visits to recovery projects.

“I traveled in Division 11 and Division 13, both to see how much progress we’ve made,” Johnson said. “Other than a few bridge projects, Division 11 is more or less done with their Helene recovery, which is remarkable since they had over $300 million in damage just two years ago.”

Johnson also described meeting Yancey County maintenance employees who have worked despite their own losses.

“These were the guys who were the frontline workers as the storm was hitting,” Johnson added. “They lost food; they lost their cars. These are the guys who are on the ground from day one, trying to reach people and help them get access. I had a great meeting with them and then took a tour of NC 197 South, where three bridges are in different stages of rehabilitation.”

Johnson then pointed to several road projects that illustrate the difference between restoring temporary access and completing permanent repairs.

“The Elk River Road, where flooding destroyed the bridge that carried traffic over the river toward the falls, and we used a temporary railcar bridge to restore traffic until a permanent structure opened in late 2025,” he said.

He also highlighted two other projects in Avery County where crews replaced damaged crossings, including another temporary railcar bridge and a new permanent bridge.

“Saw Hicks Hollow Road, where flooding destroyed the small single-lane bridge that carried traffic over the Elk River,” Johnson continued. “This was another site where we used a railcar bridge until the permanent bridge opened last month. We saw Avery High School Road, where the culvert that carried Kentucky Creek under the road washed out for the second time in 20 years. We replaced that culvert with a new bridge that opened last month.”

Johnson said those completed projects demonstrate the progress made since the storm, even as larger reconstruction efforts remain unfinished.

“Again, we’ve made tremendous strides building back stronger than we were before where we can,” Johnson said. “And we’ve still got a long way to go on some of these major projects. Long way to go to get to where we need to be before that storm hit, but incredible progress, and it was great being out there.”

While those projects have been completed, other heavily damaged roads face much longer reconstruction timelines. A Sept. 21 Polk County briefing outlined the challenges facing repairs along US 176 between Saluda and Tryon.

“We hope within a year or possibly even less to have the upper section back to normal,” NCDOT resident engineer Mike Patton said. “The lower section through the gorge will remain closed for some time. The damage down there is catastrophic, and it will take some time to fix. We are anticipating hopefully to be done by late 2029.”

Patton also addressed questions about why repairs to US 176 are taking so long, explaining that projects of this scale typically require years of planning, design and permitting before construction can begin.

“A project of this scope normally would take somewhere between six to ten years before it actually went to construction,” Patton said. “Because in front of that you have the design work, the permitting, all the environmental stuff that you have to do, everything. We managed to condense that down into just a couple of years. And the more complex these hurricane projects were, the longer it’s taken to get them out the door, even on a condensed schedule.”

Beyond the lengthy planning and permitting process, some projects face additional challenges once construction begins. On Green River Cove Road, NCDOT resident engineer Patrick Eubanks said repairs to damaged bridges and sections of roadway will require temporary closures because crews have limited space to work while maintaining traffic.

“There are also bridges on that road that have to be repaired. Two of them had major damage to them. They have to come in and replace the approach slabs on both sides of those bridges,” Eubanks said. “At some point in the process we will finish the river section, we’ll work on those bridges, and then there probably will be a hard closure of the section in the switchback so that we can start building those walls to repair those failures. There’s not a lot of room to move traffic around us while we’re working there.”

Those construction-related closures could also affect emergency services, temporarily cutting off routes currently accessible to first responders. NCDOT District Engineer Troy Wilson said transportation officials are working with emergency personnel to prepare for disruptions, although longer response times remain possible.

“We realize that emergency vehicles can use those currently, but that’s going to be temporarily suspended because they’re not going to be able to physically get through there,” Wilson said. “We continue to work with them, make sure that the schedules, they know what other unit may have to respond, you know, and we know that there’s potential extended response time.”

As Carolina Journal reported on Oct. 20, federal officials announced an additional $873 million for Hurricane Helene transportation repairs in North Carolina. The funding announcement did not change the projected completion dates for current road repairs.

The challenges illustrate the different stages of road recovery across western North Carolina. While some smaller crossings have been restored with permanent bridges, more extensive reconstruction projects remain years from completion.

Even with additional federal funding, NCDOT officials must continue navigating construction constraints, road closures, and funding challenges before all affected routes can reopen.